Time for another update !
We are making very good progress, especially on the top two floors of the main building. We have completed all the sound-proofing work in rooms 4 to 10. These rooms have all been plastered now.
The second fix plumbing has also been completed on a couple of rooms, and we have commenced tiling the rooms now. We are trying to get the top 2 floors completed in the next 30 days !
The main ceiling work has also been completed in the 2 bed flat and the Studio flat. All the sound proofing work has been done, and we plastered the ceilings in the 2 bed flat today.
The terraced houses have had the central heating systems installed, and the kitchens are almost complete. Just waiting for a few missing pieces. The appliances should all arrive at the end of next week.
The cornice work started in the houses this week, and it looks terrific. It really finishes off the rooms beautifully. Of course they will look better when the painting is complete !
We are still having problems getting the Gas, Water and Electricity connected. If anything, this is where we may have problems !
Anyway, I hope to report only good news on our next update !
Rgds
Allan